Start Date: 12/31/2015
Project: 2,500 sq/ft
Location: Michigan
Duration: 4 Days
Scope: Tile Removal, Concrete Prep and Prime, Epoxy Primer, Light Gray Epoxy Build Coat and High Traffic System Urethane Protective Topcoat (Light Gray)
PO# 5057

Start Date: 12/31/2015
Project: 2,500 sq/ft
Location: Michigan
Duration: 4 Days
Scope: Tile Removal, Concrete Prep and Prime, Epoxy Primer, Light Gray Epoxy Build Coat and High Traffic System Urethane Protective Topcoat (Light Gray)
PO# 5057