Start Date: 5-31-2016
Project: 8 Silo Roof Tops
Location: Michigan
Duration: 5 Days
Scope: Protect hand railing and non-working areas with visqueen. Use hand grinders to prep the surface and vacuum. Apply 3 coats of macropoxy, broadcasting media between coats to achieve heavily textured surface. Clean out the inside of the silo using air lance.
PO: 5487